Closing on the outside date, before the waiting period expired

Anonymised, illustrative composite. The financing commitment had a drop-dead date. So did the purchase agreement. Neither of those dates was the one that actually controlled when the deal could lawfully close.

Treadstone Associates · Updated 2026

At a glance

  • • Cross-border industrial-equipment merger, correctly identified as notifiable and properly notified; the purchase agreement's negotiated outside date fell four days before the statutory waiting period actually expired.
  • • The gap arose because the outside date was calculated from signing, while the waiting period under s.123 runs from the day the Commissioner receives the prescribed information — supplied several days after signing.
  • • Competition Act s.123.1 lets a court order remedies against a person who closes before the waiting period expires without good and sufficient cause, the proof of which lies on that person.
  • • Remedies include dissolving the completed merger or ordering disposition of assets or shares, and an administrative monetary penalty of up to $10,000 for each day of non-compliance.
  • • Believing the deal had to close by the outside date or the financing would lapse is a commercial explanation, not the statutory defence — and it did not relieve the parties of the four days' exposure.

The situation

A cross-border industrial-equipment merger was correctly identified as notifiable, and the parties did notify. The purchase agreement's negotiated outside date — the deadline after which either side could walk away if closing had not occurred — was calculated from the signing date, on the assumption that the statutory waiting period would run out comfortably before it.

The problem

The waiting period does not run from signing. It runs from the day the Commissioner actually receives the prescribed information under s.114(1), which in this deal was supplied several days after signing because of an internal delay assembling the notification package. That gap meant the purchase agreement's outside date landed four days before the statutory waiting period would actually expire. Believing the deal simply had to close by the contractual date or the financing commitment behind it would lapse, the parties closed on the outside date — four days early.

The numbers

The deal was valued at $146,000,000. It closed four days before the statutory waiting period expired. The Commissioner applied under s.123.1 roughly five months later, after completing its substantive review and identifying the closing-date discrepancy from the parties' own notification package.

The rule that decided it

Competition Act s.123.1(1) applies where a court determines that a person, “without good and sufficient cause, the proof of which lies on the person, has completed… a proposed transaction before the end of the applicable period referred to in section 123”. The proof burden sits with the party that closed early, not with the Commissioner. On these facts, an internal delay in assembling the notification package — the party's own administrative error, not something outside its control — is a weak candidate for good and sufficient cause, and a commercial deadline tied to financing is a reason to close, not a legal justification for closing before the statutory bar lifted.

Where the court finds against the party, s.123.1(1)(c) lets it order — “in the case of a completed transaction… any party to the transaction or any other person… to dissolve the merger or to dispose of assets or shares designated by the court” — and paragraph (d) separately lets it impose an administrative monetary penalty “in an amount not exceeding $10,000 for each day on which they have failed to comply with section 123”, calibrated against the person's financial position, its history of compliance, the duration of the non-compliance, and any other relevant factor. Four days of non-compliance puts the AMP's own ceiling at $40,000 before the court weighs those factors down from it — a modest number next to the transaction size, and that gap is precisely the point: the AMP alone was never the real exposure. The dissolution power is.

This is a different mechanism from s.100, which lets the Tribunal freeze a transaction before it closes, where no application under s.92 has yet been made. s.123.1 operates only after a transaction has already jumped the gun and closed — it is a remedy for the fact of premature closing, not a pre-emptive block on one that has not happened yet.

The outcome

Rather than litigate the good-and-sufficient-cause defence to a dissolution order, the parties resolved the matter with the Commissioner by consent: a modest administrative monetary penalty calibrated to the four days of non-compliance and the fact that the parties had self-reported the discrepancy once they discovered it, without the Commissioner pursuing dissolution of an already-integrated merger.

What it would have cost otherwise

The AMP was never the number that mattered. Unwinding a completed $146,000,000 industrial merger, months after two ERP systems had been integrated and workforces consolidated, would have dwarfed the AMP exposure by orders of magnitude — which is exactly why dissolution is rarely actually ordered in practice and remains, instead, the leverage that makes a consent resolution the outcome both sides have every reason to reach for.

The tell

The tell was calendaring the outside date from signing rather than from the actual statutory trigger — the date the Commissioner receives the prescribed information, which drifts from signing for entirely mundane reasons: assembling financial statements, board minutes, and the rest of a notification package. The statutory clock does not adjust itself to a negotiated commercial deadline, and a purchase agreement's outside date is not evidence of when the waiting period actually expires — it is a separate date the parties chose, calculated on an assumption that can turn out to be wrong.

Takeaways

  • • The s.123 waiting period runs from the Commissioner's receipt of the required information, not from the signing date — confirm the actual trigger date before setting a purchase agreement's outside date around it.
  • • s.123.1's good-and-sufficient-cause defence puts the proof burden on the party that closed early; an internal administrative delay is a weak candidate, and a financing deadline is a business reason, not a legal one.
  • • The per-day administrative monetary penalty is capped at $10,000, but the real exposure in a completed-transaction gun-jumping case is the dissolution power, which dwarfs the AMP on any deal of real size.
  • • s.123.1 (after-the-fact remedies for a completed transaction) is a different mechanism from s.100 (a pre-emptive freeze before closing) — know which one applies to which stage of a deal.

Sources

See where AI pays off first in your business.

A 30-minute call is enough to tell you whether AI pays for itself here.

The Canadian benchmark

What do businesses like this one actually sell for?

Canadian small-business transaction data is not published anywhere, so most valuations in this country quote an American benchmark. The Deavo–Treadstone Acquisition Index is a daily record of Canadian listings built to replace that: asking-price distributions by province and city are published now, and days on market, departure rates and asking-to-sale spreads follow as the series lengthens. Leave an email and we will tell you as each measure lands.