A cash-flow curve for each project

A schedule of values tells you what you're allowed to bill. A cash-flow curve tells you when the money from that billing actually shows up — and on most jobs, those two dates are weeks apart, every single month, for the life of the project.

Treadstone Associates · Updated 2026

Key takeaways

  • • A cash-flow curve plots three separate lines — cost incurred, amount billed, and cash actually collected — and the gaps between them, not the totals, are what a company needs to manage.
  • • Ontario's statutory holdback withholds 10% of every certified progress payment, so the cash a contractor collects is never the full amount it billed — a permanent, structural gap the curve has to model, not an exception to it.
  • • CCDC 2's stipulated-price contract “assumes monthly progress payments and makes reference to provincial payment legislations,” which is exactly why the billing rhythm and the payment rhythm run on different clocks.
  • • A three-week lookahead manages the next three weeks of work. A cash-flow curve manages the whole project's financing need — they answer different questions and a company needs both, not one instead of the other.

Most job costing systems are built to answer one question well: is this project making money. That's an accrual question — cost incurred against revenue earned — and it's the wrong question for a different, equally real problem: does the company have enough cash in the bank on the Friday payroll runs, regardless of whether the project is profitable on paper. A cash-flow curve is the tool built for that second question.

The name comes from the shape a well-run project traces when cost is plotted cumulatively against time: slow at mobilization, steep through the main body of the work, slow again as the job winds down and deficiencies get closed out — an S rather than a straight line. That shape matters for more than aesthetics. The steep middle section is where a company is financing the most work-in-progress at once, which is exactly when a gap between billed and collected does the most damage, and exactly when a curve built once at bid stage and never revisited is least likely to still match reality.

Three lines, not one

A useful project cash curve plots three separate lines against the same monthly axis, not one blended total. Cost incurred is what the crew, subs and suppliers actually cost the company that month, on an accrual basis. Amount billed is what gets certified and invoiced against the schedule of values, which usually lags cost incurred by however long it takes to compile and submit the application for payment. Cash collected is what actually clears into the bank, which lags amount billed again by the payment terms and the time an owner or GC actually takes to pay. A company that only tracks the first line looks profitable. A company that only tracks the third line is the one that runs out of cash.

The permanent gap: holdback

Even a payer with no cash-flow problems of its own doesn't pay a contractor's certified amount in full. “Every payer must hold back ten per cent of the value of the work as it is done or certified.” That 10% isn't a delay to plan around once — it's a structural, permanent gap between billed and collected on every single certification for the life of the contract, released only later, on its own separate schedule. A curve that models cash collected as 100% of amount billed is modelling a project that doesn't exist.

The billing rhythm itself is also not something a contractor sets unilaterally. CCDC 2 “assumes monthly progress payments and makes reference to provincial payment legislations where applicable,” which sets the cadence at once a month by default — a company financing weekly payroll and supplier terms against a monthly billing cycle, with a further collection lag and a 10% holdback on top, is financing a real and predictable gap, not an occasional cash crunch.

Where a lookahead stops and a cash curve starts

A three-week lookahead is the right tool for sequencing next week's crews and materials. It isn't built to answer whether the company can fund next month's payroll against a project that's profitable but slow to pay — that's a longer-horizon, whole-project financing question, and it needs its own curve, updated monthly against actual billing and collection, not derived from the schedule alone.

A worked example — one month on a $2,400,000.00 contract

In month six of a twelve-month job, the crew, subs and suppliers cost the company $260,000.00 — that's the accrual cost incurred line, and on its own it looks like a normal, on-budget month. The application for payment that month certifies $280,000.00 of progress. With the statutory 10% holdback withheld, the net amount payable on that certification is $252,000.00 ($280,000.00 × 0.90).

Cash collected that month, even before any payment-term lag, is $252,000.00 against $260,000.00 of cost incurred — an $8,000.00 shortfall for the month, on a job that is fully on schedule and on budget. Add a typical 30-day payment term on top, and the $252,000.00 doesn't land until well into the following month, while payroll and a portion of supplier invoices are due on 15- and 30-day terms of their own. The project is profitable. The month, on a cash basis, is not — and a curve that only tracked cost against billed, not billed against actually collected, would never have shown that gap coming.

The holdback comes back — on its own line

The 10% withheld each month isn't gone for the life of the project. Since 1 January 2026, accrued holdback must be released annually rather than sitting until final completion at the payer's option, which turns what used to be a single lump sum at the end of a long project into a recurring, contract-anniversary event partway through it. That release is a real cash-in date and belongs on the curve as its own line item — a multi-year project that only models holdback as an outflow, never as a scheduled return, is understating its own future cash position on the anniversary months and overstating the financing gap it actually needs to cover. The mechanics are specific enough to put directly on the curve: following each contract anniversary, the Act gives the owner 14 days to publish a notice of annual release of holdback stating the amount and the intended payment date, then 60 to 74 days from that notice to actually pay it, absent a lien still standing against the holdback — a roughly ten-week window from anniversary to cash, predictable enough to schedule for, not just a vague future release.

Building it without a dedicated tool

None of this needs specialized software to start. A monthly forecast that lists projected cost incurred, projected certified billing net of the 10% holdback, and projected cash collected against each project's actual payment terms — rolled up across every active job — is enough to see a shortfall coming a month or two out, which is the only version of this that's actually useful. A work-in-progress schedule feeds the cost and billed lines directly; the cash-collected line is the one most job costing systems don't track on their own and has to be added deliberately.

Common questions

Why isn't billed the same as collected on a construction project?

Because a statutory holdback of 10% is withheld from every certified progress payment in Ontario, and because payment terms add a further collection lag on top of that. A contractor never actually receives the full amount it bills in the same month it bills it.

Is a cash-flow curve the same thing as a schedule?

No. A schedule sequences the work; a cash-flow curve forecasts the money. They're related — billing follows progress, which follows the schedule — but a project can be perfectly on schedule and still short of cash in a given month because of holdback and payment-term lag.

How often should a project cash-flow curve be updated?

Monthly, in step with the billing cycle most contracts run on, using actual certified amounts and actual collection dates rather than the original plan — a curve built once at project start and never revisited stops reflecting what the project is actually doing within a month or two.