What OHSA paperwork does an Ontario site need?

An Ontario construction project carries a fixed, knowable set of records: a Form 1000 registration kept on site, a Notice of Project where the Construction Projects Regulation requires one, a written health and safety policy once you regularly employ more than five workers, task-specific notices for trenching, suspended platforms and asbestos, and a defined chain of notices and reports when someone is hurt. None of it is optional, and almost all of it is clerical — which is exactly why it is worth automating the filing and none of the judgment.

Treadstone Associates · Updated 2026

Key takeaways

  • • The registration form for every constructor and employer on the project (Form 1000) is not sent anywhere — it has to be at the project while you are working there.
  • • A Notice of Project is triggered by section 6 of the Construction Projects Regulation, not by a single dollar figure; the ministry publishes examples, and the complete list of triggers is in the regulation.
  • • Reporting after an injury runs on three separate clocks — immediate notification, a 48-hour written report, and a four-day written notice — plus a separate WSIB deadline of three business days.
  • • Software can file, index, remind and draft. Deciding whether an injury is critical, whether a notice is required, or whether a supervisor is competent is a person’s decision and carries a person’s signature.

The paperwork problem on a site is rarely that nobody knows the rules. It is that the rules produce a dozen small documents with different owners, different triggers and different homes, and the ones that matter most are the ones you only need on the day an inspector or a lawyer asks. What follows is the list for an Ontario project, from the ministry’s own guidance, and an honest account of which parts a machine can carry.

The documents that live on the project

Two records have to exist before work starts. The first is the registration form. The Ministry of Labour, Immigration, Training and Skills Development states that before beginning work at a project, every constructor and employer engaged in construction must complete an approved registration form (Form 1000), that the requirement sits in section 5 of the Regulation for Construction Projects (O. Reg. 213/91), and — the part people get wrong — that the form does not have to be submitted to the ministry, but must be at the project while the employer is working there. Every employer on the site needs its own. A general contractor with nine trades has ten of these, not one.

The second is the Notice of Project. Constructors must notify the ministry before construction begins on any project meeting any of the requirements in section 6 of O. Reg. 213/91. The ministry gives worked examples on the same page: a notice is required if the total cost of labour and materials is expected to exceed $50,000 where the project is confined to a factory that manufactures or assembles automobiles, or $250,000 otherwise, and it directs you to section 6 for the complete list of conditions. A signed copy of the completed form, filed online or on paper, must be posted in a conspicuous place at the project or be available at the project for review by an inspector.

Who owes these duties depends on who the constructor is. Ontario publishes a constructor guideline precisely because that question is contested on mixed sites. Our sister firm sets out the wider frame in its overview of OHSA employer basics in Ontario.

The notices that are triggered by the work, not the project

Several notices are attached to a specific operation and are easy to miss because they arrive mid-project. From the ministry’s work notice page: constructors must notify before beginning work at a project that includes work on a trench more than 1.2 metres deep into which a worker may enter; the constructor must notify at least 48 hours before a suspended work platform system is used for the first time, and keep a copy of the notice clearly visible at the worksite; notice is required before starting a Type 3 asbestos removal operation and certain Type 2 operations; and an employer with workers in Type 2 or Type 3 asbestos operations must complete an asbestos work report for each worker at least once in each 12-month period and immediately on the termination of that worker’s employment, giving a copy to the worker and keeping one on file.

The standing records back at the office

Two of the most commonly missing documents are not site documents at all. The ministry’s guide to the Act states that in workplaces where more than five workers are regularly employed, the employer must prepare a written occupational health and safety policy, review that policy at least once a year, and set up and maintain a program to implement it, and must post a copy where workers will most likely see it or make it available in a readily accessible electronic format. The same guide sets out the duty to post a copy of the OHSA and the ministry’s explanatory material, and the requirement that workers and supervisors complete a basic occupational health and safety awareness training program meeting the requirements of O. Reg. 297/13.

Supervision is a records question too. A supervisor must be a “competent person” — the guide defines that as someone qualified by knowledge, training and experience to organise the work, familiar with the Act and the regulations that apply, and aware of any potential or actual danger in the workplace. That is provable only if the training records exist. Where the site needs a joint health and safety committee, our sister firm covers when one is required in Ontario.

After an injury, three clocks run at once

This is the sequence people compress and then get wrong. Ontario’s guidance on reporting workplace incidents states that where someone is killed or critically injured, the employer or constructor must immediately notify the ministry’s Health and Safety Contact Centre, the joint health and safety committee or representative, and the union if there is one, must not disturb the scene except for the limited purposes set out in subsection 51(2) of the OHSA, and must provide a written report within 48 hours to the ministry, the committee or representative, and the union, containing the information specified by O. Reg. 420/21.

A lesser injury has its own clock. Where a person is injured and unable to do their usual work or requires medical attention, written notification must go to the committee or representative and the union within four days of the incident, and does not go to the ministry unless an inspector requires it. The same page defines “medical attention” narrowly: treatment by a physician who is a member of the College of Physicians and Surgeons of Ontario, or a Nurse Practitioner — not a chiropractor, physiotherapist or naturopath.

The third clock is the insurer’s. The WSIB requires a business to report a workplace injury or illness within three business days of learning about it where the worker needs treatment from a health professional, was absent, earns less than regular pay, or requires modified work at regular pay for more than seven calendar days, and to give the worker a copy of the report. Where the trigger is modified work at regular pay, the WSIB states that it must receive the Employer’s report of injury (Form 7) within three business days of the eighth calendar day of modified work.

The four documents most often missing when an inspector asks

1. Form 1000 for the subtrade that started yesterday. It is per employer, not per project, and it lives on site.

2. The annual review of the health and safety policy. The policy exists; the dated review does not.

3. Awareness training certificates for the two people hired in March.

4. The 48-hour written report — called in on time, never written up.

What a machine can carry, and what it must not touch

Everything above is a form, a date, or a filing decision, which is why the useful automation is unglamorous. Procore documents a Forms tool for storing and managing a project’s custom and compliance forms and a Daily Log for recording what happened on site each day. Extraction reads the paper back out — Microsoft documents Azure Document Intelligence as a service that extracts text and structured fields from documents — which is how a scanned certificate becomes a searchable expiry date rather than a PDF nobody opens.

Sensible tasks to hand over: matching each employer on site against a Form 1000 and naming the ones with none; reading training certificates into an expiry calendar; drafting the factual narrative of an incident from a supervisor’s dictated notes for a person to correct and sign; and assembling everything filed against one project into a single indexed pack when an inspector arrives.

Tasks to keep with a person: whether an injury is critical within the meaning of O. Reg. 420/21, whether a Notice of Project is required, whether a supervisor is competent, and signing anything. A model asked whether a fractured wrist is critical will answer confidently; the ministry explains that it treats the arm as including the wrist and hand, and that distinction decides whether you called the ministry or not. This is not purely a corporate risk — our sister firm covers personal liability for a workplace safety violation.

A worked example

The following is illustrative — a composite of how the workflow is usually assembled, not a measured result.

A mid-size general contractor runs four active projects. Every subtrade signs on through a single intake form capturing the Form 1000, the insurance certificate, the WSIB clearance number and the training records. Extraction pulls the dates out of each document; anything expiring inside 30 days shows on a Monday list.

When a worker cuts a hand badly enough to need stitches, the site supervisor dictates 90 seconds of notes into a phone. A draft written notification for the committee is on the health and safety manager’s screen before the worker is back from the clinic, with the four-day and three-business-day deadlines already on the calendar. The manager corrects two facts, confirms this was medical attention within the meaning of the guidance, and sends it. Nothing about the decision changed — only that the deadline was never in danger of being missed by someone who was on site all week.

Common questions

Does a small renovation need a Notice of Project?

It depends on whether the project meets any condition in section 6 of O. Reg. 213/91, which is broader than cost alone. The ministry’s work notice page gives cost examples and then explicitly directs readers to the regulation for the complete list. Treat the cost figure as one trigger among several, and have someone who can read the regulation make the call.

Can we keep all of this electronically?

For the standing office records, yes — the guide to the Act refers to posting the OHSA and the health and safety policy in a readily accessible electronic format. The site-specific notices are different: the Notice of Project must be posted conspicuously or available at the project, and the suspended work platform notice kept clearly visible at the worksite. Electronic storage does not remove a posting requirement.

Is the WSIB report the same as the ministry report?

No, and doing one does not do the other. The notices under Part VII of the OHSA are about prevention and enforcement; the WSIB Form 7 is about the worker’s claim. Different triggers, different recipients, different deadlines. If your process produces only one document, one of the two obligations is being missed.

BC runs a parallel but differently shaped system — see what a BC site must keep. If you are being audited on the system rather than the file, start with preparing for a COR audit.