Is a budget price a commitment?

Not if you keep it clearly outside the bid-call process — the label alone won't save you once a number becomes a response to an actual tender.

Treadstone Associates · Updated 2026

Short answer

Not if it stays outside the bid-call process. What creates a binding obligation under CCDC 23's framework is submitting a number in response to a tender, in the form the tender required — the word “budget” on the document doesn't change that if the substance is a bid.

What actually creates Contract A

CCDC 23 addresses “the legal obligation of owners and bidders under Contract A and Contract B” as arising through participation in a defined process: bid documents structured under Division 00 to Division 49, solicitation, closing, evaluation and award. A number becomes exposed to that framework once it's submitted as your response to that specific process — not because of what you titled the page.

Where a genuine budget number sits outside it

An early, informal figure given before any tender call exists, offered for planning purposes and never submitted through a bid solicitation, sits outside that framework. A real bid ultimately settles into one of the recognized contract structures — see stipulated price vs. cost plus for the contrast —

The channel matters as much as the label

In Ontario, trade pricing for depository-eligible work has to run through the regional bid depository to count as a formal submission at all — see how trade bids get filed. British Columbia runs the same principle through a single, centrally administered BC Construction Association depository rather than Ontario's regional ones — but in both, a number handed to a GC informally, outside that channel, doesn't become a depository bid just because the dollar figure later matches one.

Worked example: a firm gives an owner an early planning number of $3,100,000 before any tender exists. Eight months later, with drawings complete, it submits a formal bid of $3,400,000 through the actual call for tenders — a $300,000 difference. If the owner tries to hold the firm to the original figure, the firm's answer is that $3,100,000 was never submitted in response to a bid solicitation, so Contract A's framework never attached to it — the $300,000 reflects eight months of design development, not a broken promise.

a preliminary budget number is neither.

Make the difference visible on the document itself

Date it, label it clearly as preliminary, and state what it excludes, before anyone is asked to treat it as a number they can act on. An estimating system that scales covers building that discipline into how estimates get produced in the first place, so a budget figure and a bid never get confused downstream.