No — asking subtrades for quotes is asking for offers, not agreeing in advance to accept whichever one is cheapest.

Treadstone Associates · Updated 2026

Short answer

No. Requesting sub-quotes is inviting offers, not committing to the lowest one that comes back. CCDC 23 treats evaluation and selection as a distinct step in the bid process, separate from simply collecting numbers, and the same logic runs down the chain to how you pick your own subtrades.

Evaluation is a step, not a formality

CCDC 23 names “evaluation for compliance, selection, award” as its own part of the bid process, distinct from simply comparing numbers. A sub-quote that doesn't meet your scope, schedule or bonding requirements doesn't have to be carried into your own bid just because it's the cheapest figure on the page.

Two situations where the freedom narrows

Bid depository systems are the main exception: some tender processes require naming specific subtrades as part of your own compliant bid, which limits your later ability to substitute a different quote after close. Know whether you're bidding into a depository before you assume you have free choice down the chain.

The other is your own bid to the owner: if it was priced assuming a specific sub number, swapping that sub later for a cheaper one can create the same kind of pricing mismatch that makes an unbalanced bid a problem in the first place —

The depository exception isn't the same everywhere

Ontario's runs through regional associations such as the Ottawa Valley Bid Depository, releasing one set of trade numbers to every bidding GC at once. British Columbia's is centrally administered by the BC Construction Association, with its own administrator ruling on scope disputes. New Brunswick's requires advance registration with the local association before a GC can use depository numbers at all. A GC applying an Ontario-style reading everywhere may be wrong about whether an unregistered bidder's number even counts as depository pricing.

Worked example: Sub A bids $340,000 but excludes an item the drawings clearly call for; Sub B bids $362,000 and includes it. A GC that carries Sub A's number into its own $2,000,000 stipulated price, then discovers the exclusion after award, absorbs the $22,000 gap itself — its own price to the owner is already locked, so the shortfall comes out of margin, exactly what evaluating on price alone was meant to prevent.

the numbers stop matching what you told the owner they'd be.

Practical read

Put your evaluation criteria in writing before quotes come in — schedule, bonding, safety record, not just price — so “lowest” isn't the only thing anyone can point to afterward. See what compliance means in a tender for the mandatory-requirement side of the same discipline applied to your own bid.