It usually doesn’t get you out of the contract — the mistake has to be visible on the face of the bid itself, and courts set the bar high.
Short answer
Not on its own. CCDC 23 treats a compliant bid as binding the moment you submit it — the industry calls this Contract A. Canadian courts have let a bidder out only where the error is visible on the face of the bid itself, not just discovered afterward in your own working papers, and even then the bidder carries a heavy burden to prove it.
CCDC 23 names “the legal obligation of owners and bidders under Contract A and Contract B” as its own subject for a reason: the moment your compliant bid lands, it creates an obligation separate from the construction contract you’re actually hoping to win. An internal pricing error you only catch once the numbers are read out doesn’t undo that obligation — from the owner’s side, the bid still says what it says.
Ontario courts have addressed exactly this. In Manitoba Eastern Star Chalet Inc. v. Dominion Construction Co Inc., 2011 MBQB 320, the court confirmed a contractor may in theory withdraw a bid because of its own error, but only where “the non-compliance is clear from the face of the bid” and is genuinely material. The judge was explicit about why the bar sits that high: a looser rule would “effectively reward a bidder who has made a mistake in its bid, but then can utilize its non-compliance for the purposes of not honouring a contract,” so “the court will place a high burden on the bidder to demonstrate that the non-compliance is so material and substantial as to be a true non-compliance.” A number you privately know is wrong is not the same thing as a bid that visibly contradicts itself.
This is what a CCDC 220 Bid Bond exists to enforce — it guarantees “the bidder’s intention to enter into a formal contract and to provide the specified contract security if the bid is accepted.” Refuse to sign and the bond is what the owner calls on. See can we withdraw a bid after closing? for how that mechanism plays out day to day, and what a bid bond actually promises for the instrument itself.
Write to the owner immediately, don’t just quietly try to withdraw. A same-day written notice, with the error identified and shown to be apparent from the bid documents themselves rather than from your internal estimate, is the only version of this argument that has a real chance — and it only has a chance if the error would be obvious to someone reading the bid cold, not just to you. Know how long you’re actually bound to hold the price before you assume time alone gets you out.
A 30-minute call is enough to tell you whether your take-off and pricing checks would catch this before the bid goes out the door.