Anonymised, illustrative composite. An Ontario general contractor building six-storey wood-frame residential had run the same closeout ritual for years: one deficiency walk, near the very end, covering every trade at once. On the next comparable project it changed that, and the final walk found a fifth of what it used to.
At a glance
The GC had built the same unit layout, more or less, on four prior projects, and closeout had followed the same pattern every time: subtrades finished their scope, the site team let the building sit until substantial performance was close, then walked the whole thing floor by floor with every trade’s deficiencies logged at once. It worked, in the sense that the building always closed eventually. It also meant the deficiency list arrived as one large shock right when the schedule had the least slack left to absorb it.
On the prior comparable project, that single walk turned up 366 items — paint touch-ups, misaligned trim, unsealed penetrations, hardware not adjusted, the ordinary residue of a multi-trade job. Clearing it took 9 weeks, because most of the subtrades that had caused the deficiencies had already demobilized and had to be called back individually, often for a single unit’s worth of work. The Ready-for-Takeover date slipped 4 weeks waiting on it.
Of the 366, roughly 140 were painting and drywall touch-ups, 90 were trim and millwork, and the rest split across plumbing fixtures, electrical devices and door hardware — a spread across almost every trade on the job, which is exactly what makes one aggregated walk feel efficient in the moment. Scheduling a single comprehensive walk near the end looks like fewer site visits and less coordination than chasing each trade separately as it finishes. The cost of that efficiency only shows up later, once the bill for 366 individual callbacks comes due at once.
Nothing about that walk was disorganized once it started — the site team used Procore’s Punch List tool to log every item, and the tool did what it is built to do: it lets a team “keep track of remaining items to complete, assign responsibility, and maintain due dates,” with a real-time history of every action against each item. The tool was never the gap. The timing was: nothing stopped a deficiency from sitting uncaught for months, because nobody looked for it until the very end, by which point the trade responsible for it was gone and every fix competed for the same shrinking closeout window.
The GC’s own site superintendent put it plainly during the post-mortem: a misaligned door hinge found the day the drywaller finishes that unit costs one phone call. The same hinge found ten weeks later, after the drywaller has moved three jobs on, costs a callback, a scheduling delay, and usually a dispute over whether it was even that trade’s error.
The next comparable project, same GC, similar scale, ran punch walks trade-by-trade instead: as each trade signed off a floor or a unit block, that trade’s items were logged, assigned to it directly with a due date, and closed before the next trade’s work covered it up. The final walk — still run, still comprehensive, still checking everything — found 58 items instead of 366. Clearing those 58 took 8 business days. The Ready-for-Takeover date held on the original schedule.
366 items down to 58 is an 84% reduction (366 minus 58 is 308; 308 divided by 366 is just over 84%), measured against that same GC’s own prior comparable job rather than an industry benchmark. The clearing time fell from 9 weeks to under 2.
There is no regulation that dictates when a GC has to look for a deficiency. The only real constraint is economic, and it runs one direction: the cost of finding and fixing a deficiency rises every week the responsible trade is off site, because a callback replaces what would otherwise have been five minutes of in-progress correction. A single end-of-job walk is not a documentation failure — the tool logs everything it is pointed at correctly either way — it is a timing choice that guarantees every item gets found at the worst possible moment to fix it.
The Ready-for-Takeover date held, the final deficiency list was small enough to clear inside two weeks instead of nine, and no subtrade had to be recalled for a single-item callback. The practice is now standard on every multi-unit job the GC runs. For how the same discipline changes closeout timing overall, see how a school closeout ran in nineteen days, and for the underlying term see the difference between a deficiency list and a punch list.
For how firms are approaching deficiency tracking with AI tools layered on top of this kind of workflow, see AI-assisted deficiency tracking.
A 30-minute call is enough to tell you whether AI pays for itself here.