Treadstone Associates
Case File · Construction Job Costing

Margin fade traced to two cost codes

Anonymised, illustrative composite. A British Columbia civil/earthworks subcontractor watched a healthy-looking job slide toward break-even and traced the whole slide to two cost codes.

Treadstone Associates · Updated 2026

At a glance

  • • BC civil subcontractor, site-servicing package under a CCDC 4 – 2023 Unit Price Contract.
  • • Common excavation: budgeted 4,200 m³ at $38/m³; actual measured quantity 4,950 m³.
  • • Granular backfill: budgeted 1,800 t at $22/t; actual measured quantity 2,150 t.
  • • Combined unbilled revenue against actual measured quantity: $36,200.

The situation

The job looked profitable at bid stage and looked worse every month after. Job costing showed cost climbing steadily, but progress billings stayed almost flat against the original estimate. Nobody had gone back to remeasure the two cost codes actually driving the site’s volume.

The problem

The contract was a CCDC 4 – 2023 Unit Price Contract, under which CCDC states the work is priced for a “pre-determined, fixed amount for each specified unit of work performed,” with the total price determined by multiplying the unit price by the “actual, measured quantity” of work performed. The crew’s cost tracking had been reconciling actual cost against the estimated quantities from the bid takeoff, never against a field-verified re-measurement — so as actual volume ran ahead of the estimate, cost rose with it but billing did not.

The numbers

Common excavation was budgeted at 4,200 m³ at $38/m³ ($159,600). A field survey showed 4,950 m³ actually excavated. At $38/m³, that is $188,100 — $28,500 more than what the estimate had been billing against.

Granular backfill was budgeted at 1,800 t at $22/t ($39,600). The scale tickets totalled 2,150 t actually placed. At $22/t, that is $47,300 — $7,700 more than the estimate.

Together the two codes account for $36,200 of quantity the crew had genuinely placed and genuinely paid crew and material cost for, but had never billed, because nobody had submitted the re-measurement the contract entitles — and requires — the subcontractor to bill against.

The rule that decided it

CCDC 4 does not pay on the estimate; it pays on actual, measured quantity. That single clause is the whole rule, and it cuts both ways — a unit-price subcontractor who underperforms an estimated quantity is only owed for what was actually done, but one who exceeds it is owed for the excess too, provided the quantity is measured and submitted. The margin fade was not a pricing problem; it was a measurement-and-billing problem sitting on top of an otherwise correctly priced contract.

The outcome

The subcontractor submitted survey-verified re-measurement on both codes and recovered the $36,200 as a progress billing adjustment, with the field survey and scale tickets as backup. Every subsequent unit-price code on the job now gets re-measured monthly rather than left against the original takeoff. On tracking the codes themselves, see unit price contracts and quantity risk. The related overhead-allocation problem is in how a job costing rebuild exposed unbilled shop overhead, and the same firm’s progress-billing reconciliation is in what an eleven-point WIP gap turned up on another contract.

What it would have cost otherwise

Had the crew never re-measured, the $36,200 of genuinely performed, genuinely paid-for work would simply have been lost — a CCDC 4 unit-price contract pays on submitted, measured quantity, not on what a crew can later prove it did. An unsubmitted re-measurement is not a claim waiting to be made; it is revenue that was never billed and, past a certain point, becomes difficult to substantiate at all once site conditions change.

The tell

Track the ratio of actual-to-budgeted quantity on every unit-price code monthly, not only when a job's overall margin looks wrong. Excavation running 4,950 ÷ 4,200 — 18% over budgeted volume — and backfill running 2,150 ÷ 1,800 — 19% over — were both a visible, calculable early warning; the margin fade this case caught only became visible months after the quantities themselves already told the story.

Why two codes, not the whole budget, explained the fade

Every other line item on the job’s cost sheet was tracking close to its original estimate; the fade traced entirely to the two codes where actual site conditions produced meaningfully more volume than the bid takeoff assumed. That narrowness is itself useful information: a margin problem spread evenly across every cost code usually points to a pricing error at bid stage, while a margin problem concentrated in one or two codes, as here, usually points to a measurement-and-billing gap on a contract that was priced correctly in the first place. The subcontractor's monthly re-measurement schedule now flags any code running more than 10% over its budgeted quantity for review, rather than waiting for the job's overall numbers to look wrong.

What the estimate got right

The original $38/m³ and $22/t unit prices were not the problem — both held up as fair pricing once the correct quantities were billed against them. That is worth stating plainly, because a margin-fade investigation that starts by re-checking unit prices, rather than the quantities behind them, spends time on the wrong half of the contract. A unit-price job's margin depends on two independent numbers, price and quantity, and this one confirmed the price was never in question.

Takeaways

  • • A CCDC 4 unit-price contract pays on actual, measured quantity — not on the bid estimate.
  • • Cost that scales with real volume but billing that stays pinned to the estimate is margin fade with a fixed, traceable cause, not a pricing mystery.
  • • $36,200 across two cost codes came back the moment field-measured quantity replaced the estimate on the billing side.
  • • Re-measure unit-price codes on a schedule, not only when a job already looks like it is losing money.

See where AI pays off first in your business.

A 30-minute call is enough to tell you whether AI pays for itself here.