A generic chart of accounts sorts costs by kind — payroll, materials, subcontracts — the same way for every job the company runs. That's enough for a tax return. It isn't enough to tell a contractor which job, or which part of which job, is where the margin actually went.

Treadstone Associates · Updated 2026

Key takeaways

  • • Job costing runs on two axes at once: a cost code for what kind of work was done, and a cost type for what kind of cost it was — a general ledger account number alone captures neither.
  • • Procore's own default structure builds cost codes on the CSI MasterFormat's 17 divisions, in two tiers, and layers seven cost types — Equipment, Labor, Materials, Other, Owner Cost, Commitment and Professional Services — across every code.
  • • The job-costing matrix still has to reconcile to the general ledger, not run alongside it: a work-in-progress asset account and a set of cost-of-revenue control accounts are what tie the two structures together at month end.
  • • A small contractor doesn't need all 17 CSI divisions active on day one — starting with the handful the company actually self-performs, and adding divisions as the work mix changes, keeps the code list usable instead of decorative.

Every construction company already has a chart of accounts, because every company needs one to file taxes and produce financial statements. The mistake is assuming that structure is also a job-costing system. It isn't, by itself — a GL account called “Direct Labour” tells you total labour cost across every job the company ran that year. It doesn't tell you how much of it belongs to job 4417, or which part of job 4417's scope it was actually for.

Two axes, not one

Job costing needs a second dimension the general ledger doesn't carry on its own: what kind of work the cost belongs to, separate from what kind of cost it is. Procore's own field-level definition draws exactly that line: “a cost code defines the specific type of work being completed on a construction project,” and its default list is built on an existing industry standard rather than invented from scratch — the 17-division CSI MasterFormat, structured in two tiers so a division like framing or electrical can be broken down further underneath it. What a cost code actually is, and how the tiers work, is its own topic — this is about building the account structure the codes plug into.

Crossed against the cost code is cost type — not what work it was, but what kind of expense generated it. “A Cost Type is a set of costs identified by a unique abbreviation or label,” and the standard set covers Equipment, Labor, Materials, Other, Owner Cost, Commitment (subcontract) and Professional Services. Every dollar a job costs gets tagged with both: which code, and which type. A general ledger account, by contrast, usually only captures one of those two dimensions at a time.

Mapping the matrix back to the general ledger

The job-costing matrix has to reconcile to the financial statements, not run as a parallel set of books nobody ties together. Two GL structures do that work. A work-in-progress asset account carries the accumulated cost of jobs still in progress, before it's recognized as cost of revenue — the balance sheet's view of everything the code-and-type matrix has accumulated but not yet closed out. A set of cost-of-revenue control accounts, usually one per major division rather than one per individual cost code, is where completed or in-period job costs land on the income statement, summarized up from the detailed job-costing subledger underneath.

That summarization is deliberate. The income statement doesn't need, and shouldn't carry, a separate GL line for every one of dozens of cost codes — it needs a handful of control accounts that tie, in total, back to the job-costing detail. The detail lives in the job-costing system; the GL carries the roll-up.

Seventeen divisions is a ceiling, not a starting requirement

A framing and drywall subcontractor doesn't need active cost codes under all 17 CSI divisions on day one — most of them will sit unused, covering scopes the company never self-performs. Standing up codes only for the divisions the company actually works in, and adding a division deliberately when the work mix changes, keeps the code list something a foreman or bookkeeper can actually navigate, rather than a 17-division template nobody customized because it arrived pre-built.

The subcontract cost type carries one obligation the others don't: it's also the source data for T5018 reporting. A business whose income is derived primarily from construction activities has to file an information return for amounts paid or credited for goods or services rendered in the course of that activity, on either a calendar-year or fiscal-year basis once chosen, filed within six months of the reporting period's end. The definition of what counts is broader than most subcontractors expect: “construction activities” is defined to include the erection, excavation, installation, alteration, modification, repair, improvement, demolition, destruction, dismantling or removal of all or any part of a building, structure, surface or sub-surface construction, or any similar property — which pulls in far more than new-build framing and drywall. A chart of accounts that keeps subcontract payments cleanly separated under their own cost type, rather than blended into a general “other expenses” account, is what makes pulling that return together at year end an export rather than a reconstruction project.

Where committed and actual cost sit in the structure

The same code-and-type matrix is what makes tracking committed cost against actual cost possible in the first place — a purchase order or subcontract commitment gets logged against the same code and type combination the eventual invoice will hit, so the two can be compared line by line rather than only at the total. Overhead allocated from the shop and yard flows into the same structure too, usually under an Equipment or Other cost type against whichever code the labour it's allocated on relates to.

A worked example

A framing subcontractor sets up three cost codes under CSI Division 06: 06-100 for framing labour, 06-200 for framing material, 06-300 for framing equipment and allocated shop overhead. On a specific job, cost code 06-100 crossed with cost type Labor accumulates $84,000.00; code 06-200 crossed with Materials accumulates $61,500.00 of lumber and hardware; code 06-300 crossed with Equipment accumulates $9,200.00 of internal equipment charges and allocated shop overhead.

The job's total framing cost is $154,700.00 ($84,000.00 + $61,500.00 + $9,200.00). At month end, that figure rolls up into a single “Cost of Revenue — Framing” control account in the general ledger, which is all the income statement needs to see. The $154,700.00 broken into labour, material and equipment underneath it is what the job-costing detail keeps, and what a foreman comparing this job's framing cost to the last one actually has to work with.

Common questions

What's the difference between a cost code and a cost type?

A cost code identifies what work the cost belongs to — framing, electrical, sitework. A cost type identifies what kind of cost it was — labour, materials, equipment, subcontract. Job costing crosses both on every transaction; a chart of accounts alone usually only captures one.

Does a small contractor need all 17 CSI MasterFormat divisions set up?

No. Standing up cost codes only for the divisions the company actually self-performs or regularly subcontracts, and adding a division when the work mix changes, keeps the code list usable rather than a mostly-empty template.

How does job costing reconcile with the general ledger?

Through a work-in-progress asset account for costs on jobs still open, and a small set of cost-of-revenue control accounts — usually one per division rather than one per cost code — that the detailed job-costing subledger rolls up into at month end.