A congested urban site can only receive one delivery at a time through the hoist, the crane, or the laydown area it has — which makes the coordination problem a queue, not a calendar. Treating it like a scheduling exercise instead of a space-allocation exercise is why trucks end up idling at the curb.
Key takeaways
A schedule can show three deliveries arriving on the same morning without flagging a problem, because a schedule tracks dates, not the physical capacity of a hoist or a laydown pad. On an open suburban site that gap rarely matters — there's room to stage extra material and wait. On a downtown site boxed in by the property line, it's the entire problem: two trucks that both need the hoist at 9 a.m. are a conflict no schedule software flags on its own.
Treating deliveries as a booking against a limited resource — the hoist, the crane, the curb — rather than as dates on a schedule is what actually prevents the conflict, because it forces the question of who has the hoist at 9 a.m. before the truck is already on its way.
A lookahead is the tool for making a delivery date into a delivery window a site can actually staff. Procore’s lookahead tool says a lookahead's timeframe runs “a minimum of one week and a maximum of six weeks,” and that “lookaheads populate directly from the master schedule” — which keeps the near-term delivery plan honest against what the schedule actually says, rather than against a supplier's verbal promise.
One limit worth knowing: a Procore lookahead doesn't push back into an integrated external schedule tool like Microsoft Project or Primavera — it's a one-way view generated from the master schedule, not a two-way sync. Booking a delivery window against the lookahead still means confirming it against whichever schedule is the actual system of record.
Procore’s Daily Log tracks delivery entries as their own category, separate from equipment entries, dumpster entries and manpower entries — and the tool description frames it as “a central location for viewing, tracking, and emailing updates about daily project activities,” with entries recordable from a phone on site, not just from an office terminal. On a congested site, that distinction between equipment and delivery entries matters, because a truck delivering material and a crane bringing in a piece of equipment are competing for the same lift capacity even though they're logically different events.
Many Canadian downtown cores require a permit before a delivery vehicle can legally occupy a traffic lane or the curb outside a site — check with the specific municipality's roads or right-of-way department before assuming a truck can simply pull up. That permit process runs on the municipality's own timeline, not the supplier's, and it's easy to miss because it sits outside the construction schedule entirely. Toronto’s own Street Occupation Permit is a working example of what that costs in practice: its published fee schedule prices a single lane closure for a delivery vehicle, concrete truck or similar equipment/materials occupation at $73.89 plus HST per day, rising to $894.03 plus HST for a full lane closure — real numbers to budget against before assuming curb space is free.
The contract itself is where coordination of other contractors and deliveries on a shared site is supposed to live. CCDC 2, the industry-standard stipulated price contract covers “work by other contractors” as one of the roles the contract administration process addresses — which is the mechanism for resolving who has priority on the hoist or the curb when two trades' deliveries land on the same morning, rather than leaving it to whoever gets there first.
On a multi-trade downtown job, the practical fix is a shared delivery calendar owned by one person — usually the site or project superintendent — who assigns hoist or crane windows across every trade booking a delivery that week, not just the trade asking loudest. Without a single owner for that calendar, each trade books against the schedule independently and the conflicts only surface when two trucks are already on site.
A short daily huddle covering the next 24 to 48 hours of bookings against the site's actual laydown and lift capacity catches most conflicts a week out from being a problem — cheaper than resolving them at the curb with two idling trucks and two annoyed foremen.
A worked example
Say a downtown project has one hoist, and three trades each want a delivery on the same Tuesday: drywall (90 minutes to unload), a rooftop mechanical unit (2 hours, needs the crane not the hoist), and MEP rough-in materials (45 minutes). The hoist and crane aren't the same resource, so the real conflict is only between drywall and MEP for the hoist — a 135-minute combined window that fits inside a working morning if it's booked in sequence, and doesn't fit at all if both trucks show up at 8 a.m. expecting to go first.
Booking drywall for 8:00–9:30 and MEP for 9:30–10:15 against the lookahead, and confirming the crane slot for the mechanical unit separately with the crane operator, turns a three-way conflict into three non-conflicting windows — the same trucks, the same day, no idling.
Contractually, it usually sits with whoever is administering the contract — CCDC 2 frames “work by other contractors” as part of that role. Operationally, it's whoever owns the lookahead schedule and the daily log, since those are the tools that surface a same-day conflict before the trucks arrive.
Far enough that the delivery date is confirmed before it shows up in a one-to-six-week lookahead, not after — by the time a long-lead item appears in that short a window, ordering it may already be behind. See the long-lead-items article for working the vendor's lead time backward from the need-on-site date.
Treat it as a target until it's checked against the site's own constraints — hoist or crane availability, laydown space, and any municipal lane or curb permit needed. A supplier confirming a date doesn't confirm the site can actually receive the truck at that time.
Ideally it waits in a designated holding spot off the active work area rather than at the curb or in the active lift zone, until the next open window comes up on the shared delivery calendar. A site without a designated holding spot tends to solve this by improvising — a truck blocking a lane while the crew figures out where it can go — which is exactly the situation a booked-window system is meant to prevent.