Definition

Contemplated change notice, before the price

A contemplated change notice is the question, not the answer — a written request to price a possible change so the owner can decide whether to proceed, issued before any change order or change directive commits either side to anything.

Treadstone Associates · Updated 2026

How it’s used in Canada

Change orders only work if someone prices the change first, and that pricing step needs its own paper trail separate from the eventual agreement. A contemplated change notice is that step: the consultant or owner describes a possible change and asks the contractor to return a price and a schedule impact, without yet instructing the work to proceed. Treadstone Law’s guidance on protecting a change claim applies just as directly to this earlier stage — "get change orders in writing whenever possible, even a brief confirming email" — because a contemplated change notice that never gets written down is just as hard to prove later as a verbal change order.

What happens after the notice depends on what the owner decides once the price comes back. If the parties agree the price, it typically becomes a change order: a documented agreement before the work begins. If the owner needs the work started before a price is agreed, the consultant can instead issue a change directive, ordering the work to proceed while the price from the contemplated change notice is negotiated or determined afterward. Either way, the notice itself commits nobody to anything — it exists so that a price exists to negotiate over, rather than the first number on the table being the contractor’s invoice.

Worked example

A consultant on an office fit-out project spots a conflict between the mechanical drawings and a client’s furniture layout and issues a contemplated change notice asking the contractor to price relocating four ceiling diffusers. The contractor returns a price of $9,400 and a two-day schedule impact within the notice’s stated response window. The owner reviews the number, decides it is reasonable, and the parties sign a change order at that price before the relocation work starts — the contemplated change notice did its job by putting a real number in front of the owner before any diffuser was touched.

Related terms

See also: Change order vs change directive · Cash allowances in a contract · Change order management that avoids disputes.