The irrevocable period is the length of time, stated in the tender documents themselves, during which a submitted bid stays open for acceptance and cannot be withdrawn by the bidder.
The doctrine behind it is Canadian, not contractual boilerplate. As a major national law firm's guide to procurement explains, submitting a bid in response to a tender call itself forms a contract — commonly called "Contract A" — separate from the construction contract the parties sign later ("Contract B") if the bid is accepted. That framework comes from the Supreme Court of Canada's decision in The Queen (Ont.) v. Ron Engineering & Eastern Construction (Eastern) Ltd., which first articulated the Contract A / Contract B analysis. One of the defining terms of Contract A, per that guide, is that "submissions/bids are irrevocable for a defined period of time" — the tender documents set the length, not a fixed rule of law, and it is not the same on every project.
Because the period is contractual rather than statutory, a bidder cannot assume any particular number of days applies. It is fixed by the specific instructions to bidders for that tender, and it typically runs from the bid closing date, not from the date the bid was prepared.
A trade contractor submits a bid depository price for a hospital HVAC package. The tender documents state the bid is irrevocable for a set number of days after closing. During that window the general contractor is entitled to rely on the price to build its own stipulated bid, and the trade contractor cannot walk away from it even if it discovers a pricing error the next morning — the fix, in practice, is to build a contingency into the number before closing, not to plan on withdrawing after.
See also: Addenda: the late changes that bind your bid · Bid depository: how trade bids get filed.
A 30-minute call is enough to tell you whether AI pays for itself here.