Definition

Percentage of completion revenue

Percentage-of-completion is the accounting method that recognizes a long-term contract's revenue in proportion to how much of the work is actually done in a given period, rather than waiting until the entire contract is finished to book any of it.

Treadstone Associates · Updated 2026

How it's used in Canada

Under Canadian ASPE, CPA British Columbia's guidance on ASPE Section 3400, paragraph 3400.06, states plainly that performance on a long-term contract shall be determined "using either the percentage of completion method or the completed contract method, whichever relates the revenue to the work accomplished" and that the alternative — the completed-contract method, which defers everything to the end — "would only be appropriate when performance consists of the execution of a single act or when the enterprise cannot reasonably estimate the extent of progress toward completion." For a multi-month construction contract with a working cost estimate, that leaves percentage-of-completion as the method that generally applies.

The common version of the method is cost-to-cost: percent complete is costs incurred to date divided by the total estimated cost to complete the contract, and revenue recognized for the period is that percentage of total contract revenue, less whatever revenue was already recognized in earlier periods. Comparing that earned-revenue figure against what has actually been invoiced is exactly where overbilling and underbilling come from.

Worked example

A contract is worth $1,000,000, with total estimated cost to complete of $800,000. Costs incurred to date are $320,000. Percent complete is $320,000 ÷ $800,000 = 40%. Revenue recognized to date is 40% × $1,000,000 = $400,000, and gross profit recognized to date is $400,000 minus $320,000 = $80,000 — a figure that can sit well above or below whatever the contractor has actually invoiced under its own progress-billing schedule, which is precisely the gap a WIP schedule is built to track.

Related terms

See also: Overbilling vs underbilling · The WIP schedule your bank asks for.