A surety and a bank are underwriting the same firm from two different angles at once. A package built once, to both audiences, is faster to assemble and harder to poke holes in than two separate improvised submissions.
Key takeaways
STEP 01 OF 10
CCDC's own bond forms cover three distinct guarantees: the bid bond (CCDC 220), which guarantees the bidder's intention to enter the contract and provide the specified security if selected; the performance bond (CCDC 221), which guarantees the contractor's performance of the contract itself; and the labour and material payment bond (CCDC 222), which guarantees all labour and material payment obligations under the contract. Confirm exactly which of the three — often all three — the tender actually requires before assembling anything else.
See bid bond — what it promises, performance bond — who it protects and labour and material payment bond for what each one specifically obligates the contractor and the surety to.
STEP 02 OF 10
A surety and a bank both start from the same document: current financial statements, ideally review-engagement or audited rather than internally prepared, showing the firm's actual balance sheet position, not a projection. A package that leads with project experience and bonding history before the financials is presenting the story before the evidence — put the numbers first.
Confirm the working-capital ratio the statements imply before submitting anything. BDC frames a healthy range as roughly 1.5 to 1.75 in current assets for every dollar of current liabilities. A package with a ratio well below that range is not automatically declined, but it invites the first question a surety asks, so have the explanation ready rather than reactive.
STEP 03 OF 10
WSIB states plainly that a clearance is valid for up to 90 days, and that it auto-renews only for as long as the business stays current on both WSIB payments and reporting. A clearance pulled two months before a bid closes may already be within days of expiring by the time the surety or bank actually reviews the package.
Pull the clearance as the last step before submission, not the first — the opposite order from most of the rest of the package, which benefits from being assembled early. A clearance is the one document in the package that actively decays while the rest of the file is being put together.
STEP 04 OF 10
CCDC 11 — the same contractor's qualification statement an owner's pre-qualification process would request — is equally useful to hand a surety directly: company information, financial references, key personnel, and project experience across completed, comparable and currently-underway work, all in one standardized format. If the firm has already prepared one for a tender, reuse it rather than rebuilding the same disclosure from scratch for the surety.
See tendering a major capital project for how CCDC 11 gets used on the owner side of the same disclosure — keeping the two consistent avoids a surety noticing a discrepancy between what was told to an owner and what was told to the bank.
STEP 05 OF 10
EDC's own description is direct: the APSG is “the only solution in Canada that gives your financial institution a 100 per cent guarantee for standby letters of credit,” letting the bank issue bid, performance, advance-payment, warranty and supplier guarantees without the contractor pledging cash or other assets as collateral. EDC assumes 100 per cent of the bank's risk instead, keeping the contractor's working capital available for the project itself.
There is no cost to set up an APSG — fees only apply if the lender actually draws on the facility, at a pre-negotiated rate. The process runs in three steps: the contractor contacts EDC, EDC works with the contractor and its bank to establish pre-approved coverage, and the bank then issues guarantees using the APSG as the collateral replacement. Most contractors preparing a bonding package never ask about this option and default straight to pledging their own collateral.
STEP 06 OF 10
CCDC 11's own project-experience section asks for five relevant projects across completed, comparable and currently-underway categories — which means bonding capacity is effectively a running track record, not a single approval a firm gets once. Keep the qualification statement current on a rolling basis so a new bonding request is an update to an existing file, not a first-time submission every time.
See bonding capacity and its ceiling for how a surety actually thinks about the aggregate ceiling across a firm's concurrent projects, not just the single project a specific bond request is for.
STEP 07 OF 10
A surety or bank package built from numbers that do not match the firm's own monthly close or job cost reports is a discrepancy waiting to be found in underwriting. Pull the package's figures directly from the same reconciled sources the firm already relies on internally, rather than reconstructing a separate set of numbers for external presentation.
A surety that catches even a small, explainable discrepancy between the package and the underlying books will scrutinize everything else in the file harder as a result. Consistency is worth more than any single number looking marginally better in the external version.
STEP 08 OF 10
A surety reviewing a rolling financial history will find a bad quarter regardless of whether the contractor raises it first. Presenting it proactively, with a specific explanation and what changed afterward, reads very differently from a surety discovering it unexplained inside a stack of statements and asking why it was not mentioned.
See contractor lost bonding after one bad quarter for what the alternative to disclosure actually costs when a surety finds the problem on its own.
STEP 09 OF 10
A rolling 13-week cash forecast is forward-looking evidence a static set of financial statements cannot provide on its own — it shows the surety or bank the firm actively manages cash rather than discovering shortfalls after they happen. Include the current forecast, or a recent snapshot of one, alongside the historical statements.
A bank in particular tends to respond well to seeing an active forecasting discipline, since it signals the firm is more likely to flag a covenant risk early than let it surface as a missed payment.
STEP 10 OF 10
A surety relationship built on periodic, proactive updates — even when no specific bond is currently needed — produces a faster, easier conversation the next time one is. Set a recurring cycle, tied to the firm's own fiscal year-end and updated financial statements, to refresh the whole package rather than treating every bonding request as the first time the surety has seen the firm's current numbers.
Asking generically for “bonding” instead of naming the specific bond form. Bid, performance, and labour-and-material payment bonds guarantee three different things. A vague request leaves the surety guessing what is actually needed.
Pulling the WSIB clearance early and letting it sit in the file for weeks. A clearance is valid for up to 90 days. Pull it last, immediately before submission, not first.
Assuming full cash collateral is the only way to secure a bond. EDC's Account Performance Security Guarantee exists specifically to remove that assumption, at no cost to set up. Most contractors never ask.
Letting a bad quarter surface unexplained instead of disclosing it with a plan attached. See contractor lost bonding after one bad quarter for what an undisclosed problem, found by the surety rather than raised by the contractor, actually costs.
Building the package's figures separately from the firm's own monthly close and job cost data. A discrepancy between the external package and the internal books, even a small and explainable one, invites harder scrutiny of everything else in the file.
Two figures a bonding package needs right, with specific numbers and dates for demonstration only.
Collateral relief from an APSG. A contractor needs a $500,000 combined bid and performance bond package for a project. Without an APSG, the bank requires the full $500,000 tied up as cash-secured collateral before it will issue the guarantees. With an APSG in place, EDC guarantees 100 per cent of the bank's risk instead, and that same $500,000 stays available as working capital for the project — the collateral requirement itself, not just its cost, is what the APSG removes.
A clearance that has gone stale. A WSIB clearance is issued January 1. The bid the package supports closes April 15 — 104 days later. At up to 90 days' validity, the clearance expired 14 days before the bid even closed. A package submitted with that January 1 clearance attached is submitted with a document that will not hold up to a straightforward date check, regardless of how strong the rest of the file is.
Neither problem is difficult to avoid once it is on the checklist — but both are exactly the kind of detail that gets missed when a bonding package is assembled once and reused across several submissions without re-checking each date and figure against the specific submission date.
The province a firm mostly works in changes how much of its own billed revenue is sitting in retained holdback at any given time — which is part of what a surety is assessing in the working-capital ratio.
A firm bidding across more than one province should model its working-capital ratio separately for each province's holdback rate, rather than assuming one blended figure captures the real difference in how quickly cash actually comes back.
Early enough that the financial statements and CCDC 11 qualification statement are ready well ahead of time, but with the WSIB clearance pulled last, since it is the one document in the package that actively expires while everything else can sit ready.
No — EDC states there is no cost to set it up. Costs only apply if the lender actually draws on the facility, at a pre-negotiated rate agreed in advance.
Not necessarily — but how it is disclosed matters. See contractor lost bonding after one bad quarter for what happens when a surety finds a problem the contractor did not raise first.
Both. Historical financial statements show where the firm has been; a current 13-week cash forecast shows the surety or bank that the firm is actively managing what comes next, which is a different kind of evidence.
A 30-minute call is enough to tell you whether it is worth building.