The tracker that works is built on two fields nobody thinks of as accounting: the date each proper invoice was received, and whether a notice of non-payment went back. Under Ontario’s prompt payment rules, those decide what is owed as much as the arithmetic does.
Key takeaways
The tracker that stays current is built on two columns nobody thinks of as a tracker field: the date each proper invoice was received, and whether a notice of non-payment was delivered in response. Under Ontario’s prompt payment regime those two facts decide what is owed as much as the arithmetic does.
Per subcontract, and updated as the job runs: the original contract value; approved changes; the value certified to date; the holdback retained; the amount invoiced; the amount paid; the date each invoice was received; and, for each invoice, whether it was paid, partly paid, or answered with a notice of non-payment, and when.
The reason the date of receipt has to be a real field rather than a note is that the legislation attaches consequences to it. Everything else in the list is accounting. That one is a clock.
Ontario’s Construction Act sets fixed timelines for responding to a proper invoice. Our sister firm summarises the mechanism: an owner who receives a proper invoice from a contractor must pay it, or deliver a valid notice of non-payment setting out the specific reasons for withholding, within the timelines the Act sets, and a similar cascading obligation applies as payment flows down the chain to subcontractors. Where a party neither pays nor delivers a valid non-payment notice in time, they generally lose the ability to dispute that amount later and simply owe it.
The Authorized Nominating Authority for construction adjudication in Ontario records that the Act was amended on 1 October 2019 to include the requirement for prompt payment of proper invoices, with non-payment referable to adjudication, and that further amendments to the Act came into force on 1 January 2026. For a fuller walk-through of the rules and what happens when payment is disputed, Treadstone Law has a detailed note on prompt payment timelines.
The operational consequence is stark. Silence is not neutral. A tracker whose exception report is “invoices we have not paid” is looking at the wrong thing; the report that matters is “invoices we have neither paid nor formally disputed, where the response window is running”.
The three exception reports worth having
Response clock running. Proper invoices received, not yet paid, with no notice of non-payment delivered. This is the report that prevents an accidental admission.
Certified but unpaid. Work valued and approved, invoice raised, payment not released — the sub’s view of what they are owed today.
Retained, not owed yet. Holdback accrued per subcontract, with the date it becomes releasable, so it is never confused with an overdue balance.
The single most common distortion in a subcontractor payment tracker is treating retained holdback as arrears. It is neither owed nor free: it is withheld by statute and becomes payable on its own timetable. Our sister firm explains what a holdback is and when it can be released. Keep it in its own column with its own date, or every ageing report you produce will overstate what you owe and understate what you are holding.
There is a second reason to know exactly who is owed what. Amounts received on a construction project are subject to trust obligations, which is a different claim from a lien and has different consequences for the people who direct the payments. Treadstone Law covers how a trust fund claim works under the Construction Act and, at more length, what happens when trust funds are misused. A tracker that shows, per project, what came in and what went out to the trades on that project is the record that answers a trust question later.
Three specific jobs, none of which involve deciding whether to pay.
Reconciling invoices to commitments. Matching an incoming sub invoice to the right subcontract and the right approved changes is dull, repetitive comparison work. Construction platforms model this natively — Procore documents its Commitments tool for subcontracts and purchase orders — and a model can do the matching where the numbers arrive as PDFs rather than as data.
Flagging the clock. Reading the received date off an invoice and raising it before the response window closes is exactly the sort of deadline arithmetic software should own.
Drafting the notice. If a payment is being withheld, the notice has content requirements and has to state the specific reasons. A model can assemble a first draft from the site record — the deficiency log, the schedule, the correspondence — and a person checks it, decides whether to send it, and signs. The decision to withhold is never the software’s.
A construction business has an information return to file on what it paid its subcontractors. The Income Tax Regulations require that a person or partnership paying or crediting amounts for goods or services rendered in the course of construction activities must make an information return, where its business income for the period is derived primarily from those activities, on either a calendar-year or fiscal-period basis, with the return due within six months after the end of the reporting period. Once the reporting period is chosen it cannot be changed for later years without the Minister’s authorisation.
A payment tracker that already holds the legal name, the business number and the total paid per sub turns that filing into an export. One that does not turns it into a week of reconstruction.
Illustrative — the shape of the workflow, not a measured result.
A general contractor with nine active projects receives sub invoices by email. Each is stamped with its received date automatically on arrival, matched to a subcontract, and compared against the approved change orders on that subcontract. Anything that does not match — a line item with no approved change behind it, a value above the certified amount — is held for the project manager rather than queued for payment.
Every Monday the system produces the three exception reports above. The one that changed behaviour was the first: two invoices where the response window was running and nobody had decided anything. Both were disputable on the merits; neither had been disputed in writing. Producing that list took no human time, and it is the list that costs money when nobody produces it.
The Construction Act sets content requirements, and the adjudication authority notes it does not publish a template of a proper invoice, directing users to the provisions of the Act. Because it is a legal test rather than a formatting preference, the sensible operational move is to agree the invoice format with each sub at contract signature so the question does not arise monthly.
It depends on the project’s timing. The adjudication authority lists four versions of the legislation that may apply to a project, with transition rules in the Act itself, and advises consulting a construction lawyer to determine which applies. That is a field on the project record, not a fact to be re-derived every time a question comes up.
No. Withholding without delivering a valid notice in time is precisely the failure the regime penalises. Automate the alert and the draft; leave the decision, and the signature, with a person. If a dispute is already live, our sister firm sets out the options in a contractor-subcontractor payment dispute.