Everyone remembers it rained. Nobody remembers the exact millimetres, the exact station, or the exact date three months later — and a weather delay claim runs entirely on those specifics, not on the fact that it happened.
Key takeaways
Environment and Climate Change Canada's historical data search lets anyone query recorded daily observations by station, with year selection running from 1840 through the current year and filtering by specific month and day. That's the actual evidentiary source for a weather delay — not a recollection of a bad week, but a specific, citable reading tied to a specific station near the site, for the specific date in question.
The station matters as much as the date. Weather varies enough over even modest distances that the reading from the nearest station with a complete record, not the nearest city by name, is what should back a claim.
Climate normals are something else entirely: 30-year averages built from composite stations with at least 15 years of data in the 1991–2020 period, describing typical conditions for a location, not what happened on any particular day. They're the wrong tool for proving a delay and the right one for planning — for example, deciding how much schedule contingency a typically wet season in a given region warrants before the project even starts. Confusing the two is a real trap: a 30-year average for “usual” conditions in a month proves nothing about what actually happened on the specific days a crew was stood down.
The two tools serve two different moments in a project's life. A normal belongs in the estimate and the schedule float, decided before the first shovel goes in the ground. The daily record belongs in the delay claim, pulled after the fact for the exact dates in dispute. Reaching for the wrong one at either moment weakens the argument being made.
Treadstone Law's summary of how Ontario courts read force majeure clauses is direct about the standard: the event has to fit the categories the clause actually lists, and it has to genuinely prevent performance — not just make it more expensive or less convenient. Foreseeable events are harder to excuse. And critically, the party invoking the clause carries the burden: give notice promptly, document the event, show a genuine connection between the event and the non-performance, and demonstrate reasonable efforts to work around it.
A pulled daily-data record is exactly what discharges that documentation burden. Without it, a weather delay claim is an assertion that it was bad out there; with it, it's a dated, sourced fact a counterparty or an adjudicator can independently verify against the same public record.
CCDC 20's guide to construction contract administration treats correspondence as the working record of how a contract was actually administered — and a weather day that was never mentioned in any correspondence at the time it happened is a much weaker claim months later, however accurate the historical data eventually pulled to support it turns out to be. The prompt notice a force majeure clause requires and the correspondence trail a contract administrator relies on are, in practice, the same document.
A file that can withstand scrutiny has four pieces, none of them optional: the pulled station data for the specific dates and the specific nearest station; the diary entries logged the same days, noting who stood down and what work was affected; the prompt notice sent to the contract administrator or owner at the time, not reconstructed afterward; and, where the clause requires it, some record of what was tried to work around the delay before conceding the day was lost entirely.
Missing any one of the four weakens the others. Station data with no contemporaneous notice looks like an argument assembled after the fact to fit a dispute; a diary entry with no station data is an unverified assertion about conditions; a prompt notice with neither is just a claim of inconvenience, not a documented delay. Where the weather-driven stoppage also affects work that's about to be covered up, a dated photo of the affected area adds a fifth piece worth having.
A worked example
A week of freezing rain stops exterior work in early spring. The superintendent notes the stand-down in the site diary each day it happens, and sends a short notice to the contract administrator flagging the delay — both done the same week, not reconstructed later.
Weeks later, when the delay becomes a schedule dispute, the actual evidentiary record gets assembled: the nearest station's historical daily data for each affected date, cross-referenced against the diary entries and the correspondence sent at the time. The claim isn't “it rained a lot that week” — it's a specific, dated, sourced account: these dates, this station, these readings, this contemporaneous notice.
Compare that to a claim built after the fact with no contemporaneous notice: even with the same historical data pulled later, a force majeure argument that shows up for the first time in a dispute, with no prompt notice at the time, is far weaker — the notice requirement itself is part of what the clause demands, not an optional formality.
Yes — the historical daily data search covers specific dates at specific stations, with records reaching back to 1840. That's the source to pull for a weather delay claim, not a general recollection or a seasonal average.
Not directly. Climate normals describe typical, averaged conditions over a 30-year period, not what happened on any specific day. They're useful for planning schedule contingency before a project starts, not for substantiating that a particular week was actually a weather stoppage.
Prompt notice, documentation of the event, a genuine causal link to the non-performance, and reasonable efforts to work around it — and the burden of proving all of that sits with the party invoking the clause, not the other side.
Yes. The value of logging it at the time, in the site diary and in correspondence, is that it's there if a dispute arises later — and a contemporaneous note costs almost nothing to make, while reconstructing one after the fact is far harder and far less persuasive.
No — a single day of unpleasant conditions that doesn't actually stop the work in progress is a different case than a day the trade in question genuinely could not safely or practically proceed. The record needs to show the conditions actually prevented the specific work, not just that conditions were worse than ideal.