An as-built is the contractor’s own working markup of what actually got installed, kept current on site; a record drawing is the clean, verified version compiled from those markups and handed to the owner once the project closes out.
Procore’s construction management glossary defines both terms: “An As-Built Drawing is a document that shows how a finished product was installed.” Its companion entry for record drawings is worded almost identically, and that’s exactly the point of confusion — the same source: “Record Drawings show how a finished product was installed with all changes to ensure accurate documentation of completed work.”
The practical difference on a Canadian job site is in when each document is produced and who relies on it. As-builts are the field markups — often required by the contract to be kept current continuously, reviewed at each progress draw, and never fully “finished” until the job is. Record drawings are the deliverable: a formal, sometimes re-drafted, compiled set produced at or after substantial performance, checked against every trade’s as-builts, and issued to the owner as part of the closeout package alongside the operation and maintenance manuals.
That closeout package matters well beyond handover day — it’s the reference the next renovation, tenant fit-out or emergency repair relies on, which is exactly why CCDC’s standard contract administration guidance treats closeout documentation as prerequisites tied to the takeover of the project, not paperwork that can be produced later on nobody’s schedule.
A mechanical contractor relocates a floor drain 400mm from its drawn position during rough-in. The site superintendent marks the change on the working set that same day — that markup is the as-built. At substantial performance, the consultant pulls every trade’s as-built markups together, checks them against what was actually built, and issues a single clean set of record drawings to the owner. Two years later, when a tenant fit-out needs to know exactly where that drain sits, it’s the record drawing — not the original design set, and not the superintendent’s field markup — that gets pulled from the file.