Definition

Commissioning vs turnover

Commissioning is the technical proof that a building’s systems actually work as designed; turnover is the separate, contractual act of handing the project — and possession — from contractor to owner. They usually happen close together, but one can finish before the other.

Treadstone Associates · Updated 2026

How it’s used in Canada

Procore’s glossary defines commissioning precisely: “Commissioning (Cx) is the formal process of verifying that some or all of a structure and its assemblies and systems (such as heating, ventilation, and air conditioning (HVAC), elevator control, fire suppression, and more) have been designed, installed, tested, and operated in accordance with the project’s intended use and contract requirements.”

Canadian standard-form contracts don’t generally use the word “turnover” as a defined term — CCDC 2’s stipulated-price contract instead sets out prerequisites for Ready-for-Takeover, tied to reaching substantial performance. What a general industry glossary calls turnover, a CCDC 2 contract frames as satisfying those Ready-for-Takeover conditions and completing the possession process the contract sets out from there.

The two processes are genuinely independent, which is the whole reason they need separate terms. A system can pass every commissioning test and still not be turned over, because outstanding items — captured on the “Punch List” — “a document that records incomplete or defective work items requiring attention before project completion” — still block the contract’s takeover conditions. Equally, possession can change hands with commissioning still outstanding on some systems if the contract allows it, which is exactly the situation a careful owner tries to avoid by keeping the two checklists separate rather than treating “done” as one event.

Worked example

A data centre’s UPS and cooling systems pass every commissioning test two weeks before the contractor is scheduled to hand over keys and documentation. Commissioning is complete — the systems work as designed. Turnover hasn’t happened yet, though, because a dozen punch-list items — a mislabelled panel, an unfinished access door, missing as-built markups on two mechanical rooms — still stand between the project and the Ready-for-Takeover conditions in the contract. The building is technically ready to run; it isn’t yet the owner’s to run.

Related terms

See also: What substantial performance actually means · As-builts vs record drawings.