Type 1, 2 and 3 are Ontario’s three-tier risk classification under O.Reg 278/05 for construction or repair work that disturbs asbestos-containing material, and the tier — not the job as a whole — determines what precautions, notice and worker certification the law requires.
Type 1 (low risk) covers installing or removing ceiling tiles over less than 7.5 m², non-friable asbestos-containing material (ACM) that is not broken, cut, drilled or ground, wetted non-friable ACM disturbed only with non-powered hand tools, and removing less than 1 m² of drywall with asbestos-containing joint compound. Type 2 (medium risk) covers removing false ceilings, disturbing less than 1 m² of friable ACM, enclosing friable ACM, and work with HEPA-filtered power tools; Type 3 (high risk) covers removing more than 1 m² of friable ACM, spray-applying sealants to friable ACM, and non-HEPA power tools.
Certification is mandatory for Type 3 work but not required for Type 1 or Type 2, and Ontario requires advance notice before a Type 3 removal operation and certain Type 2 operations, plus an asbestos work report for each Type 2 or Type 3 worker at least once every 12 months and immediately on termination of employment.
A contractor removes drywall containing asbestos joint compound from a 15 m² wall and, on the same job, removes non-friable ceiling tile over a separate 6 m² area. The 15 m² drywall removal exceeds the 1 m² friable-material threshold, so that portion is Type 3 — requiring advance notice and Type-3-certified workers. The 6 m² of non-friable tile removal independently qualifies as Type 1 on its own facts, so uncertified crew can do that portion of the same job while only certified workers touch the drywall.
See also: COR: the certificate of recognition · What OHSA paperwork does an Ontario site need? · Using AI to write a construction incident report.
A 30-minute call is enough to tell you whether AI pays for itself here.